Wanna solve challenging Time and Work Questions? If yes, here is the best practice material for you. We are providing Practice Test on Time and Work and quiz along with solutions. You have to practice so many questions to improve your time management skills. With the help of the below-mentioned practice question and answers, you will come to know the various types of questions asked in the exam. Evaluate your performance with the help of the questions given below.

Practice Test on Time and Work

1.  X alone can do a piece of work in 8 hours while Y alone can do it in 12 hours. Both X and Y together can complete the work in how many days?

A. 21/4 Hours

B. 10 Hours

C. 5 Hours

D. 24/5 Hours

Solution: D (24 /5 Hours)

2. Worker X takes 8 hours to do a job. Worker Y takes 10 hours to do the same job. How long it will take when both X and Y are working together but independently, on the same job?

A. 40/9

B. 60/3

C. 44/2

D. 55/4

Solution: A (40/9)

3. X and Y together can complete a piece of work in 4 days. If X alone can complete the same work in 12 days. In how many days can Y alone can complete that work?

A. 4 Days

B. 6 Days

C. 12 Days

D. 24 Days

Solution: B (6 Days)

4. X is twice as good as a workman as Y and together they can finish a piece of work in 18 days. How many days will X alone will take to complete the work?

A. 27 Days

B. 24 Days

C. 15 Days

D. 20 Days

Solution: A (27 Days)

5. 45 men can finish a job in 16 days. 30 more men joined working, 6 days after they initiated working. How many days more will they now take to finish the remaining work?

A. 15 Days

B. 10 Days

C. 6 Days

D. 8 Days

Solution: C (6 Days)

Quiz on Time and Work Problems

6. X, Y, and Z can complete a piece of work in 24,6 and 12days respectively. In how many days, they will finish the complete work?

A. 4 Days

B. 8 Days

C. 10 Days

D. 15 Days

Solution: A (4 Days)

7. 3 boys and 3 men can complete a piece of job in 10 days while 2 boys and 2 men can complete the same piece of job in 8 days. How many days can 2 men and 1 boy finish the work?

A. 60/4

B. 25/2

C. 20/2

D. 15/3

Solution: B (25/2)

8. X and Y undertake to do a piece of work for Rs.600, X alone can do it in 6 days while Y alone can do it in 8 days. By taking the help of Z, they complete it in 3 days. Find each member’s share?

A. Rs.300, Rs.225, Rs.75

B. Rs.500, Rs.100, Rs.55

C. Rs.200, Rs.75, Rs.50

D. Rs.400, Rs.200, Rs.100

Solution: A (Rs.300, Rs.225, Rs.75)

9. X can do a piece of job in 12 days. Y is 60% more efficient than X. If Y alone works, then how many days he will take to complete the work?

A. 8.5 Days

B. 9 Days

C. 7.5 Days

D. 7 Days

Solution: C (7.5 Days)

10. X can work 5 times faster than Y and takes 60 days less compared to B to complete the work. How many days do A and B take individually to complete the work?

A. 20 Days, 60 Days

B. 15 Days, 75 Days

C. 25 Days, 80 Days

D. 15 Days, 50 Days

Solution: B (15 Days, 75 Days)

Time and Efficiency Quick Mock Tests

11. If 24 men can finish the work in 10 days, then find the number of days required to complete the same work by 30 men?

A. 12 Days

B. 15 Days

C. 8 Days

D. 20 Days

Solution: C (8 Days)

12. X can finish the work in 3 days. Y can finish the same piece of work in 6 days and Z can do the same piece of work in 7 days. How many days X, Y, and Z take to complete the job together?

A. 14/9 Days

B. 24 Days

C. 18 Days

D. 15/6 Days

Solution: A (14/9 Days)

13. P and Q can do the work in 12 days. Q and R can do the same work in 16 days, R and P can do it in 24 days. Find the number of days in which P, Q, and R can finish the work together?

A. 30/4 Days

B. 32/3Days

C. 60/4 Days

D. 70/6 Days

Solution: B (32/3 Days)

14. If 3 men can finish a job in 2 days and 4 boys can finish the same job in 6 days. Then, how many days will 8 men and 8 boys take to finish the same job?

A. 30/5 Days

B. 5/30 Days

C. 10/6 Days

D. 6/10 Days

Solution: D (6/10 Days)

15. Gita and Sita can complete a job in 20 days and 25 days respectively. Both start the job together but Gita leaves the job after a few days. After Gita leaves the job, Sita completes the work in 10 days. After how many days did Gita leave?

A. 20/3 Days

B. 60/4 Days

C. 20 Days

D. 15 Days

Solution: A (20/3 Days)

Practice Test on Time and Work – Worksheets

16. When P alone does the job, he takes 25 days more than the time taken by P and Q working together to finish the work. But Q alone takes 9 days more than the time taken by P and Q working together to finish the work. In what time P and Q together will finish this work?

A. 10 Days

B. 20 Days

C. 15 Days

D. 25 Days

Solution:  C (15 Days)

17. X can complete the job in 20 days. X and Y together can complete the job in 12 days. How long does Y take to finish that job?

A. 20 Days

B. 40 Days

C. 30 Days

D. 15 Days

Solution: C (30 Days)

18. Pipe X can fill the complete tank in 40 minutes. Pipe Y alone can fill the tank in 60 minutes. X and Y together can fill the complete tank in how many mins?

A. 120 mins

B. 60 mins

C. 40 mins

D. 80 mins

Solution: A (120 mins)

19. X can complete the work in 20 days, Y in 30 days, and C in 40 days. All of them started working together. But after 5 days, X left. After 3 more days Y also left the work. Z can complete the remaining work in how many days?

A. 35/6 Days

B. 34/3 Days

C. 45/7 Days

D. 60/8 Days

Solution: B (34/3 Days)

20. W can complete the work in 25 days, X in 30 days, Y in 50 days, Z in 75 days. W and X started working together and later Y joined after 7 days of work. After 3 more days Z replaced X. After 2 more days, W and Y left the work. In how many days did Z complete the work?

A. 8/3

B. 9/2

C. 6/2

D. 10/6

Solution: B (9/2)